Clove Lakes Park Fitness Equipment Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the adult fitness equipment in Clove Lakes Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: April 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Clove Lakes Park , Staten Island
Brooks Pond Place and Martling Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 08/07/2020