Audubon Playground Comfort Station Reconstruction
-
100% complete
-
100% complete
-
38% complete
This project will reconstruct the comfort station at Audubon Playground and make it ADA accessible.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: November 2016
Projected Completion Date:
November 2017
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
October 2019
Construction
Start Date: January 2020
Projected Completion Date:
April 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Audubon Playground
, Manhattan
Audubon Avenue between West 169th Street and West 170th Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/26/2021