Audubon Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will reconstruct the comfort station at Audubon Playground and make it ADA accessible.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: October 2019

Construction

Start Date: January 2020
Projected Completion Date: April 2021
Adjusted Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Mayoral

Location

Audubon Playground , Manhattan
Audubon Avenue between West 169th Street and West 170th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/18/2022

Was this information helpful?