Bronx, Manhattan and Queens Reforestation FY18

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees in the Bronx, Manhattan and Queens.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Various locations in the Bronx. Manhattan and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 05/24/2018