Bronx, Manhattan and Queens Reforestation FY18

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees in the Bronx, Manhattan and Queens.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Various locations in the Bronx. Manhattan and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/18/2018