Brooklyn, Queens and Staten Island Reforestation FY18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees in Brooklyn, Queens, and Staten Island.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: December 2018

Construction

Start Date: January 2019
Projected Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $1,280,000
Funding Source: Mayoral

Location

Various locations in Brooklyn, Queens, and Staten Island.

Project Staff

Contact NYC Parks about this project

Last updated: 01/19/2019