Melrose Commons Site 62 Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    99% complete

This project will construct a park at Melrose Commons Site 62, including a synthetic turf field, adult fitness equipment, a dog run, seating areas, drinking fountains, lighting, fences, pavement, plantings, and drainage.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: January 2022

Construction

Start Date: February 2022
Projected Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $9,355,000
Funding Source: Mayoral

Location

A. Badillo Community Rose Garden and Park , Bronx
Melrose Avenue between East 162nd Street and East 163rd Street

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 10/04/2022