Pelham Bay Park Sensory Garden Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a barrier-free participatory garden that engages all the senses in enjoying the outdoors in Pelham Bay Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Pelham Bay Park , Bronx
Bruckner Boulevard and Middletown Road next to Playground For All Children

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project