Woodlawn Playground Spray Shower Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the spray shower at Woodlawn Playground in Van Cortlandt Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: March 2018
Projected Completion Date:
February 2019
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
November 2019
Adjusted Completion
Date:
February 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Van Cortlandt Park
, Bronx
Van Cortlandt Park East between Oneida Avenue and Kepler Avenue
Project Staff
Project Liaison: Michelle Martell