St. James Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    17% complete

This project will construct a dog run in St. James Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021
Completion Date: May 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $831,000
Funding Sources:
  • City Council
  • Mayoral

Location

St. James Park , Bronx
Creston Avenue and East 193rd Street

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 08/05/2022

Was this information helpful?