Manhattan Community Garden Water Service Installation

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will install water service lines at various community gardens in Manhattan.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: June 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Borough President

Locations

  • 103 East 122nd Street
  • East 8th Street between Avenues C & D
  • Lexington Avenue between East 100th and East 101 Streets
  • Pleasant Avenue between East 118 & East 119 Streets
  • West 126th Street between St. Nicholas & Frederick Douglass

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/17/2018