Manhattan Community Garden Water Service Installation

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will install water service lines at various community gardens in Manhattan.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: June 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Adjusted Completion Date: November 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • 103 East 122nd Street
  • East 8th Street between Avenues C & D
  • Lexington Avenue between East 100th and East 101 Streets
  • Pleasant Avenue between East 118 & East 119 Streets
  • West 126th Street between St. Nicholas & Frederick Douglass

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/19/2020