Willis Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the play area at Willis Playground.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: December 2017
Projected Completion Date:
December 2018
Completion Date:
January 2019
Procurement
Start Date: January 2019
Projected Completion Date:
October 2019
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Willis Playground
, Bronx
East 141st Street between Alexander Avenue and Willis Avenue
Project Staff
Project Liaison: Michelle Martell
Contact NYC Parks
about this project
Last updated: 02/21/2019