Devoe Park Dog Run Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run at Devoe Park.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: January 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $796,000
Funding Sources:
  • Mayoral
  • City Council

Location

Devoe Park , Bronx
West Fordham Road, Webb Avenue, Father Zeiser Place, University Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/04/2021