Playground 174 Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    43% complete

This project will reconstruct play and adult fitness equipment, swings, spray shower, pavements, fencing, lighting, and mini-pool.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: November 2018

Construction

Start Date: October 2018
Projected Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $3,986,000
Funding Source: Mayoral

Location

Playground 174 , Bronx
East 174th Street between Bronx River Avenue and Manor Avenue.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/18/2019