Playground 174 Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct play and adult fitness equipment, swings, spray shower, pavements, fencing, lighting, and mini-pool.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Playground 174, Bronx
Located at East 174th Street between Bronx River and Manor Avenues.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/16/2018