Playground 174 Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Playground 174.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: November 2019

Construction

Start Date: March 2020
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $1,890,000
Funding Source: Mayoral

Location

Playground 174 , Bronx
East 174th Street between Bronx River Avenue and Manor Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/27/2020