Playground 174 Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Playground 174.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: November 2019

Construction

Start Date: January 2021
Projected Completion Date: January 2022

Understand how we build parks.

Funding

Total Funding: $1,890,000
Funding Source: Mayoral

Location

Playground 174 , Bronx
East 174th Street between Bronx River Avenue and Manor Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/27/2020