Mapes Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    59% complete

This project will reconstruct Mapes Ballfield with a new natural turf outfield, recreational sports lighting, play equipment, and adult fitness equipment.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: July 2019
Completion Date: July 2019

Construction

Start Date: November 2019
Projected Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $10,780,000
Funding Source: Mayoral

Location

Mapes Ballfield , Bronx
Mapes Avenue and Prospect Avenue between East 180th Street and East 181st Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 07/05/2020