Mapes Ballfield Reconstruction
-
100% complete
-
100% complete
-
92% complete
This project will reconstruct Mapes Ballfield with a new natural turf outfield, recreational sports lighting, play equipment, and adult fitness equipment.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
November 2018
Procurement
Start Date: November 2018
Projected Completion Date:
July 2019
Completion
Date:
July 2019
Construction
Start Date: November 2019
Projected Completion Date:
November 2020
Adjusted Completion
Date:
March 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Mapes Ballfield
, Bronx
Mapes Avenue and Prospect Avenue between East 180th Street and East 181st Street
Project Staff
Project Liaison: Michelle Martell
Contact NYC Parks
about this project
Last updated: 04/15/2021