Mapes Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    90% complete

This project will reconstruct Mapes Ballfield with a new natural turf outfield, recreational sports lighting, play equipment, and adult fitness equipment.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: July 2019
Completion Date: July 2019

Construction

Start Date: November 2019
Projected Completion Date: November 2020
Adjusted Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $12,530,000
Funding Source: Mayoral

Location

Mapes Ballfield , Bronx
Mapes Avenue and Prospect Avenue between East 180th Street and East 181st Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/15/2021