Broad Channel Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the entry plaza, including new benches, pavement and fencing, at Broad Channel Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: April 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: June 2021

Construction

Start Date: July 2021
Projected Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $269,000
Funding Sources:
  • Borough President
  • City Council

Location

Broad Channel Park , Queens
East 16th Road, Cross Bay Boulevard, Channel Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/19/2021

Was this information helpful?