Broad Channel Park Reconstruction
-
100% complete
-
100% complete
-
45% complete
This project will reconstruct the entry plaza, including new benches, pavement and fencing, at Broad Channel Park.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
April 2019
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
November 2019
Completion
Date:
June 2021
Construction
Start Date: July 2021
Projected Completion Date:
July 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Broad Channel Park
, Queens
East 16th Road, Cross Bay Boulevard, Channel Road
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 05/20/2022