Challenge Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    72% complete

This project will reconstruct the play equipment, fencing, and spray shower area at Challenge Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $3,075,000
Funding Sources:
  • Borough President
  • City Council

Location

Challenge Playground , Queens
251st Street between 61st Avenue and 63rd Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/04/2021

Was this information helpful?