Whitey Ford Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the natural turf baseball field at Whitey Ford Field.
Project Timeline
Design
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
December 2019
Completion
Date:
April 2020
Construction
Start Date: October 2020
Projected Completion Date:
October 2021
Completion
Date:
June 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Whitey Ford Field
, Queens
26th Avenue between 1st Street and 2nd Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/01/2022