Whitey Ford Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the natural turf baseball field at Whitey Ford Field.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: April 2020

Construction

Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $2,993,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Whitey Ford Field , Queens
26th Avenue between 1st Street and 2nd Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/01/2022

Was this information helpful?