Fairview Park Multi-Purpose Field and Landscape Construction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will construct a multi-purpose field, baseball field, tennis courts, pickleball courts, adult fitness equipment, picnic area, parking area, bio-retention areas, paths, and landscape elements at Fairview Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Fairview Park , Staten Island
Arthur Kill Road and Veterans Road West

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/16/2018