Fairview Park Multi-Purpose Field and Landscape Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    70% complete

This project will construct a multi-purpose field, baseball field, tennis courts, pickleball courts, adult fitness equipment, picnic area, parking area, bio-retention areas, paths, and landscape elements at Fairview Park.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: December 2018

Construction

Start Date: February 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $19,300,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal

Location

Fairview Park , Staten Island
Arthur Kill Road and Veterans Road West

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 06/01/2020