Fairview Park Multi-Purpose Field and Landscape Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    92% complete

This project will construct a multi-purpose field, baseball field, tennis courts, pickleball courts, adult fitness equipment, picnic area, parking area, bio-retention areas, paths, and landscape elements at Fairview Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Completion Date: December 2018

Construction

Start Date: February 2019
Projected Completion Date: August 2020
Adjusted Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $19,300,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • Federal

Location

Fairview Park , Staten Island
Arthur Kill Road and Veterans Road West

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project