Brooklyn and Staten Island Park Trees Planting and Replacement

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will plant new park trees in Brooklyn and Staten Island.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: December 2017
Adjusted Completion Date: July 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various locations in Brooklyn and Staten Island

Project Staff

Contact NYC Parks about this project

Last updated: 08/17/2018