Bronx, Manhattan and Queens Park Trees Planting and Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    46% complete

This project will plant new park trees in the Bronx, Manhattan and Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: December 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Source: Mayoral

Location

Various locations in the Bronx, Manhattan and Queens

Project Staff

Contact NYC Parks about this project