Bronx Green Infrastructure Construction (XG-418M)

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture stormwater at Crotona Parkway Malls, Whalen Grove, Parkside Playground, Loreto Playground, and Haviland Playground.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: December 2018
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 08/20/2019