Bronx Green Infrastructure Construction (XG-418M)

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture stormwater at Crotona Parkway Malls, Whalen Grove, Parkside, Loreto and Haviland Playgrounds in the Bronx.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: December 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 02/16/2018