Parkside Playground Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture stormwater at Parkside Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: December 2018
Completion Date: June 2020

Procurement

Start Date: June 2020
Projected Completion Date: March 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Parkside Playground , Bronx
Arnow Avenue, Olinville Avenue.

 

Project Staff

Contact NYC Parks about this project

Last updated: 12/01/2020