Fairview Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

The construction of a comfort station and related site work at Fairview Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Fairview Park, Staten Island
Bricktown Way between Arthur Kill Road & Veterans Road West

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 02/16/2018