NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Bronx Park Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct an adult fitness area in Bronx Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline


Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: November 2017


Start Date: November 2017
Projected Completion Date: August 2018


The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.


Total Funding: Less than $1 million
Funding Source: City Council


Bronx Park , Bronx
Bronx Park located at Burke Avenue, East 180th Street between Dr. Kazamiroff Boulevard, Southern Boulevard and Bronx Park East, Unionport Rd.


Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 03/16/2018

Was this information helpful?