Highbridge Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a comfort station in Highbridge Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: February 2021

Construction

Start Date: July 2021
Projected Completion Date: October 2022

Understand how we build parks.

Funding

Total Funding: $4,242,000
Funding Source: Mayoral

Location

Highbridge Park , Manhattan
Edgecombe Avenue between West 164th Street and West 165th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/22/2021

Was this information helpful?