Highbridge Park Comfort Station Construction
-
100% complete
-
100% complete
-
0% complete
This project will construct a comfort station in Highbridge Park.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
February 2021
Construction
Start Date: July 2021
Projected Completion Date:
October 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highbridge Park
, Manhattan
Edgecombe Avenue between West 164th Street and West 165th Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 08/15/2022