Queens PlaNYC Street Tree Planting FY18 - Community Boards 7,8,11

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    97% complete

This project will plant new trees in Community Boards 7, 8, and 11 in Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: August 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $3,330,000
Funding Source: Mayoral

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 09/30/2020