Brooklyn PlaNYC Street Tree Planting FY18 - Community Boards 11,13,15

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will plant new trees in Community Boards 11, 13, and 15 in Brooklyn.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: August 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 08/17/2018