Bronx Street Tree Planting FY18 - Community Boards 1-8

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    76% complete

This project will plant new trees in Community Boards 1-8 in the Bronx.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: August 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Adjusted Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Source: Mayoral

Location

Various locations in the Bronx

Project Staff

Contact NYC Parks about this project

Last updated: 11/27/2020