Highbridge Anchor Park Reconstruction Phase II

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    64% complete

This project will reconstruct Adventure Playground and Sunken Playground, install park pathway lighting to the historic High Bridge, and construct a new synthetic turf practice field at Highbridge Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $13,410,000
Funding Sources:
  • Mayoral
  • State

Location

Highbridge Park , Manhattan
Along Edgecombe Avenue between West 163rd and West 166th Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/05/2020