Highbridge Anchor Park Reconstruction Phase II

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    3% complete

This project will reconstruct Adventure Playground and Sunken Playground, install park pathway lighting to the historic High Bridge, and construct a new synthetic turf practice field at Highbridge Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $14,040,000
Funding Sources:
  • Mayoral
  • State

Location

Highbridge Park , Manhattan
Along Edgecombe Avenue between West 163rd and West 166th Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/23/2019