Bloomingdale Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct basketball courts, paths, benches, spray shower, planting, play equipment and adult fitness equipment at Bloomingdale Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $4,189,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bloomingdale Playground , Manhattan
Amsterdam Avenue between West 104th Street and West 105th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/15/2018