NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Bloomingdale Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct basketball courts, paths, benches, spray shower, planting, play equipment and adult fitness.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Adjusted Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bloomingdale Playground, Manhattan
Amsterdam Avenue, between West 104th Street and West 105th Street.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/23/2018

Was this information helpful?