Flushing Meadows Corona Park Lawrence Playground Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct Lawrence Playground in Flushing Meadows Corona Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: May 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: February 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $10 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
Bounded by the Van Wyck Expressway, Botanical Garden Bridge and College Point Boulevard, Borough of Queens

 