Flushing Meadows Corona Park Lawrence Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Lawrence Playground in Flushing Meadows Corona Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: May 2017
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
Bounded by the Van Wyck Expressway, Botanical Garden Bridge and College Point Boulevard, Borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project