Betsy Head Park Synthetic Turf Field, Track, Sport Courts and Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a synthetic turf field, rubberized track, sport courts and adult fitness equipment area at Betsy Head Park.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: September 2019
Projected Completion Date: February 2021
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $18,150,000
Funding Source: Mayoral

Location

Betsy Head Park , Brooklyn
Livonia Avenue, Strauss Street and Dumont Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/29/2021

Was this information helpful?