Betsy Head Park Synthetic Turf Field, Track, Sport Courts and Adult Fitness Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a synthetic turf field, rubberized track, sport courts and adult fitness equipment area at Betsy Head Park.
Project Timeline
Design
Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
June 2019
Construction
Start Date: September 2019
Projected Completion Date:
February 2021
Completion
Date:
November 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Betsy Head Park
, Brooklyn
Livonia Avenue, Strauss Street and Dumont Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 08/05/2022