Alley Pond Park Living Shoreline Construction Phase 2

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a living shoreline along the western shore of Alley Creek at Alley Pond Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: May 2022

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Adjusted Completion Date: February 2023

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Cross Island Parkway , Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard

 

Project Staff

Contact NYC Parks about this project

Last updated: 08/12/2022

Was this information helpful?