Alley Pond Park Living Shoreline Construction Phase 2
-
100% complete
-
5% complete
-
0% complete
This project will construct a living shoreline along the western shore of Alley Creek at Alley Pond Park.
Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.
Project Timeline
Design
Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
May 2022
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Adjusted Completion
Date:
February 2023
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Location
Cross Island Parkway
, Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard
Project Staff
Contact NYC Parks about this projectLast updated: 08/12/2022