Bill 'Bojangles' Robinson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    86% complete

This project will reconstruct Bill 'Bojangles' Robinson Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,047,000
Funding Source: Mayoral

Location

Bill Bojangles Robinson Playground , Manhattan
West 150th Street between Frederick Douglass Boulevard and Adam Clayton Powell Jr. Boulevard

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/03/2020