Bill 'Bojangles' Robinson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Bill 'Bojangles' Robinson Playground.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Bill Bojangles Robinson Playground , Manhattan
West 150th Street between Frederick Douglass Boulevard and Adam Clayton Powell Jr. Boulevard

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/16/2019