Playground One Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Playground One.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: April 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,453,000
Funding Source: Mayoral

Location

Playground One , Manhattan
Madison Street between Oliver Street and Catherine Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/15/2021