Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
July 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion
Date:
December 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Joseph C. Sauer Park
, Manhattan
East 12th Street between Avenue A & Avenue B
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 05/27/2022