Harlem Lane Playground and Frederick Johnson Playground Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Harlem Lane Playground and Frederick Johnson Playground, including the comfort station, stairs, sports areas, lighting, plantings, paths, benches, and sidewalks. The project will reestablish the connection between the upper and lower portions of the park and may introduce new features like a walking and bike path.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: February 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • State

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/10/2018