Prospect Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    84% complete

This project will reconstruct Prospect Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $6,535,000
Funding Source: Mayoral

Location

Prospect Playground , Bronx
East 176th Street between Clinton Avenue and Prospect Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 10/23/2021