Prospect Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Prospect Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $6,685,000
Funding Source: Mayoral

Location

Prospect Playground , Bronx
East 176th Street between Clinton Avenue and Prospect Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 08/16/2022