Chappetto Square Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Chappetto Square.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Chappetto Square , Queens
Hoyt Avenue North, 21st Street, 23rd Street, and 24th Drive

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/15/2018