Brooklyn Green Infrastructure Construction
-
100% complete
-
5% complete
-
0% complete
This project will construct green infrastructure to capture storm water at Classon Playground, Colonel David Marcus Playground and Oracle Playground.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
December 2018
Completion Date:
April 2021
Procurement
Start Date: April 2021
Projected Completion Date:
January 2022
Adjusted Completion
Date:
October 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Classon Playground, Brooklyn
Lafayette & Classon Avenues -
Colonel David Marcus Playground, Brooklyn
Ocean Parkway, Avenue P, East 3 Street -
Oracle Playground, Brooklyn
Adelphi & Myrtle Avenues
Project Staff
Contact NYC Parks about this projectLast updated: 07/05/2022