Queens Green Infrastructure Construction (QG-518M)

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture storm water at East Elmhurst Playground, Electric Playground, Horace Harding Playground, London Planetree Playground, and Joseph P. Addabbo Memorial Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: June 2019
Adjusted Completion Date: June 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/15/2019