Queens Green Infrastructure Construction (QG-518M)

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture storm water at East Elmhurst Playground, Electric Playground, Horace Harding Playground, London Planetree Playground, and Joseph P. Addabbo Memorial Park.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: June 2019
Adjusted Completion Date: February 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/28/2020