Bloomingdale Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort station in Bloomingdale Playground, bringing it into compliance with ADA accessibility standards.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $1,509,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Bloomingdale Playground , Manhattan
Amsterdam Avenue between West 104th Street and West 105th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project