Highbridge Bathhouse Boiler Reconstruction and Air Conditioning Construction
-
100% complete
-
85% complete
-
0% complete
This project will reconstruct boilers and related plumbing and provide a new heating, ventilating, and air conditioning system for Highbridge Bathhouse.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: December 2016
Projected Completion Date:
March 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
August 2019
Adjusted Completion
Date:
April 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highbridge Park
, Manhattan
2301 Amsterdam Avenue
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/26/2021