Highbridge Bathhouse Boiler Reconstruction and Air Conditioning Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct boilers and related plumbing and provide a new heating, ventilating, and air conditioning system for Highbridge Bathhouse.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: March 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Completion Date: April 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Highbridge Park , Manhattan
2301 Amsterdam Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/22/2021

Was this information helpful?