Battery Park Coast Guard Monument Relocation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will relocate the Coast Guard Monument in Battery Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: May 2017
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Construction

Start Date: August 2020
Projected Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $600,000
Funding Source: Private

Location

The Battery , Manhattan
State Street and South Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/05/2020