Battery Park Coast Guard Monument Relocation

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will relocate the Coast Guard Monument in Battery Park.

Project Update: Design is complete.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: May 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Private

Location

The Battery , Manhattan
State Street and South Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/19/2018