Battery Park Coast Guard Monument Relocation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will relocate the Coast Guard Monument in Battery Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: May 2017
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Construction

Start Date: April 2020
Projected Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $600,000
Funding Source: Private

Location

The Battery , Manhattan
State Street and South Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/31/2020