Wingate Park Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    22% complete

This project will reconstruct the basketball courts at Wingate Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,203,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Wingate Park , Brooklyn
Winthrop Street between Brooklyn Avenue and Kingston Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/02/2020