Sakura Park Stairs Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the staircase at the northeast corner of Sakura Park. The work will include a new foundation and resetting the existing granite steps and walls.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: January 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,213,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Sakura Park , Manhattan
West 122nd Street between Riverside Drive and Claremont Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/28/2020