Sakura Park Stairs Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the staircase at the northeast corner of Sakura Park. The work will include a new foundation and resetting the existing granite steps and walls.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: January 2020

Construction

Start Date: March 2020
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $2,213,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Sakura Park , Manhattan
West 122nd Street between Riverside Drive and Claremont Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/24/2020