Wagner Playground Synthetic Turf Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the combination soccer and baseball synthetic turf field and adjacent fencing, drinking fountains, and seating areas at Wagner Playground.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Adjusted Completion Date: December 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Wagner Playground , Manhattan
Second Avenue between East 120th Street and East 121st Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/13/2019