Wagner Playground Synthetic Turf Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the combination soccer and baseball synthetic turf field and adjacent fencing, drinking fountains, and seating areas at Wagner Playground.

Project Timeline

Design

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: December 2019

Construction

Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $2,300,000
Funding Source: Mayoral

Location

Wagner Playground , Manhattan
Second Avenue between East 120th Street and East 121st Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/17/2021