Morningside Park Middle Playground and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    38% complete

This project will reconstruct Middle Playground and the basketball courts at Morningside Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: June 2019
Completion Date: October 2019

Construction

Start Date: December 2019
Projected Completion Date: December 2020
Adjusted Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $4,374,000
Funding Sources:
  • Borough President
  • City Council

Location

Morningside Park , Manhattan
Morningside Drive and 118th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/29/2020