Bronx, Manhattan and Queens Sandy-Related Park Tree Planting and Replacement FY18

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will plant new trees in parks affected by Hurricane Sandy in the Bronx, Manhattan and Queens.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: June 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various locations in the Bronx, Manhattan and Queens.

Project Staff

Contact NYC Parks about this project

Last updated: 11/16/2018