Bronx, Manhattan and Queens Sandy-Related Park Tree Planting and Replacement FY18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in parks affected by Hurricane Sandy in the Bronx, Manhattan and Queens.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: June 2017
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: April 2021
Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $2,740,000
Funding Sources:
  • Mayoral
  • Federal

Location

Various locations in the Bronx, Manhattan and Queens.

Project Staff

Contact NYC Parks about this project

Last updated: 06/18/2021

Was this information helpful?