Abraham Lincoln Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    36% complete

This project will reconstruct the comfort station in Abraham Lincoln Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2017
Projected Completion Date: February 2018
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: March 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Adjusted Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $1,640,000
Funding Source: Mayoral

Location

Abraham Lincoln Playground , Manhattan
Fifth Avenue and East 135th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/19/2020